Project summary
New build - Mechanical system installations
Complete Mechanical System buildout for boiler, chiller, and glycol refrigeration systems for 3 Wegmans Grocery stores.
Excel was given HVAC and refrigeration maintenance contracts for all MD sites, based on excellent project performance and start-up support.
See below for the full case study
-
Wegmans Grocery Store
-
Alexandria, VA, Washington, DC, Rockville, MD
-
Commercial Retail
-
Mechanical System installations for 3 new Wegmans grocery stores in mixed use buildings utilizing hydronic heating and cooling systems.
-
Full build-out of (3) chiller and boiler system mechanical rooms, Nexus Hybrid coolers, AHUs, and FCUs. Fully coordinated and 80% pre-fabrication builds.
-
2 Years
-
Fast-paced projects with 2 running concurrently. Overcame COVID related suppy-chain challenges.
The Challenge
Tight-timelines with two projects running concurently and supply chain issues causing equipment delays.
The Solution
Excel utilized BIM coordination and pre-fabrication to hit tight schedule targets, allowing for efficient and accurate installation. This allowed the team to stay on schedule while managing two locations simultaneously. Excel's team demonstrated their collaborative approach by working with the customer and suppliers to complete the project on-time despite equipment delays.
The benefits
-
Timely mechanical systems installations allowed for customer sites to be open on schedule
-
New equipment provides energy efficient operation and customer comfort
-
Stores were able to open on schedule and provide customers with a comfortable experience
The Team's take
Excel's team successfully executed 3 new store builds for Wegmans, providing them with high-quality piping and equipment systems and on schedule installation. Excel built a strong relationship with the customer by providing excellent installation, and demonstrating our expertise in mechanical systems, resulting in an expanded facility support partnership.